Published in 2018 at "IEEE Industry Applications Magazine"
DOI: 10.1109/mias.2016.2600682
Abstract: While preparing a modern data center for startup, the commissioning process involved primary circuit switching that resulted in two voltage transformer (VT) failures. As a result, we conducted a comprehensive investigation of the VT failures.…
read more here.
Keywords:
solution implementation;
voltage transformer;
transformer failures;